Prest Road Roundabout and Road Widening – McGuire to Bailey

Paving on Prest Road will be rescheduled weather permitting. The new schedule will be posted when it's available.

Current Works

Construction began on Prest Road between Bailey Road and McGuire Road in July. At times, traffic will be single lane alternating on Prest Road. Please obey the direction of traffic control personnel, expect delays and take an alternate route if possible.

Aug 2026.jpg

Timeline

Fall 2025: Archeological field investigation completed.
Winter 2025/2026:
Hydro and Telus utility pole relocations completed.
Spring 2026: Archeological permitting received and construction tender awarded to Ballina Contracting.
Summer 2026: Road construction began with completion prior to winter.

Project Details

The third and final phase of the Prest Road widening project from McGuire Road to Bailey Road began in 2025 with completion in 2026. This phase includes the construction of a roundabout at Prest Road and McGuire Road and road widening between McGuire Road and Bailey Road.

Location of Project-mr3pko2s_v.jpgTo minimize disruptions, the City completed the culvert replacement at Interception Ditch on Prest Road during the 2024 fish window.

Want to Learn More?

Do you have any questions about the Prest Road Roundabout and Road Widening from McGuire Road to Bailey Road? Please see our Frequently Asked Questions and Information Sheet. You can also contact the Engineering Department at 604-793-2907 or [email protected].

For updates on transportation construction projects, subscribe to our e-newsletter.

Attachments
Description Date File Size 
Frequency Asked Questions 2025-10-23 249KB 
Prest Road Information Sheet 2025-07-09 513KB