2021 Sidewalk Projects

Strathcona/Crystal Sidewalk

 

Construction Timeline:

  •  Summer 2021

    • Council awarded the works to Contour Concrete Ltd.
    • Surveying, sewer, curb and gutter work to be completed in July.
    • Paving, sidewalks, and landscaping to be completed in August.
    • Streetlight bases are to be installed in August however, streetlighting will be installed in the fall due to delays in streetlight pole manufacturing. 
    • Please anticipate minor delays throughout the duration of the project.

Project Works:

  • Sidewalks and curb repairs are substantially complete on Crystal Drive.
  • Curb, gutter, and sidewalk forms completed on the west half of the sidewalk project.  The rest of the curb, gutter, and sidewalk to be completed on the east side of the project later in August.
  • Surveying and site preparation complete along length of project.
  • Coordination of the Hydro pole movement ongoing with BC Hydro.
  • Frontage improvements will not be taking place in front of 46527 due to future projects at that location.
  • Every effort was made to keep the trees in front of the school, however, the west tree was removed due to it being unhealthy.  A healthy replacement tree will be replanted at the end of the project.

To Ask us a Question:

For monthly updates on transportation construction projects, subscribe to our e-newsletter.


Tyson Road Sidewalk

Project Details:

A new sidewalk and LED street lighting has been installed on Tyson Road between Keith Wilson Road and Sardis Sports Complex to improve safety for children walking and cycling to Mt. Slesse Middle School.

Construction Timeline:

  • Complete

Project Works:

  • The sidewalk and restoration complete.
  • One streetlight has been installed.

For monthly updates on transportation construction projects, subscribe to our e-newsletter.