 Notification  17791
 Street Main Street 9299
 Description Activities pertain to the installation of building facade elements, installation of street lighting conduits, forming and concrete placement of landscaped planter walls. The pavement and foundation water proofing, and concrete of the municipal sidewalk. Work will necessitate the extension of workers via boom lifts and these lifts need to articulate and position themselves on Princess Ave to maximize project schedules efficiency and allow concurrent work to process with landscapes concrete.
 Time Periods Thursday January 8, 2026 - Saturday February 7, 2026 (7:00AM - 6:00PM)
Monday January 12, 2026 - Saturday February 7, 2026 (7:00AM - 6:00PM)