86

specified below in relation watercourse classes A

through E.

5. “Top of bank” means the point closest to

the boundary of the active floodplain of a

watercourse where a break in the slope of the

land occurs such that the grade beyond the

break is flatter than 3:1 (3 horizontal / 1 vertical)

at any point for a minimum distance of 15 meters

measured perpendicularly from the boundary of

the active floodplain.

6. “Top of ravine bank” means the first significant

break in a ravine slope where the break occurs

such that the grade beyond is flatter than 3:1 (3

horizontal / 1 vertical) for a minimum distance

of 15 metres measured perpendicularly from the

break, and the break does not include a bench

within the ravine that could be developed.

Watercourse Classification:

The Watercourse Map (Map 8A) identifies the clas-

sification of the inventoried watercourses within the

City of Chilliwack as follows:

Development Permit Required

As set out on the OCP Watercourse Map (Map 8A)

and Village West Riparian Setbacks Map (Map 8B),

the following activities require a Development Per-

mit:

1. Development within 30m of the top of bank of a

watercourse classified as Class “A”.

2. Development within 30m of the top of the bank

of a watercourse classified as Class “B”, where

the existing or potential adjacent vegetation is

continuously over 30m wide.

3. Development within 15m of the top of bank of

a watercourse classified as Class “B”, where the

existing or potential adjacent vegetation is less

than 30m wide.

4. Development within 15m of the top of bank of a

watercourse classified as Class “C”.

5. Development within 7.5m of the top of bank of a

watercourse classified as Class “D”.

6. Development within the setbacks from top of

bank as indicated on the Village West Riparian

Setbacks Map (OCP Map 8B).

7. Development within 30m of the top of bank of a

watercourse classified on the Watercourse Map,

as “E” (unclassified) unless it is tributary to Class

“C” or “D” watercourse; in which case the dis-

tance shall be 15m to 7.5m respectively.

8. Development within 30m of the top of bank of

an unmapped watercourse identified at time of

development unless it is tributary to Class “C” or

“D” watercourse; in which case the distance shall

be 15m and 7.5m respectively.

Exemptions

The following activities are exempted from the

requirements for a Development Permit:

1. Farming operations as defined in the Farm

Practices Protection Act;

2. Reconstruction or repair of a permanent

structure remaining on its existing foundation;

and

3. Development not associated with or resulting

from residential, commercial or industrial

activities.

The above exemptions do not remove setbacks

requirements from watercourses stipulated by the

City of Chilliwack Floodplain Regulation Bylaw that

is in force from time to time. In the event of any

inconsistency between the guidelines of this DPA and

other DPAs, the former shall prevail.

Guidelines

1. In compliance with the Riparian Areas Regulation,

development may be permitted if the City is

notified by the appropriate federal and provincial

ministries that they have been notified of the

development proposal, and provided with a copy

of an assessment report prepared by a QEP that:

a. Certifies that they are qualified to carry out

the assessment;

Implementation Guide